Pilot guided auger drilling Railway Arnhem Central 

Last week, during daytime services at Railway Arnhem Central, we installed realized two 42-metre railwaytrack crossings (EGP tube ø100), crossing seven tracks with each drilling. The advantage of drilling with EGP tube is that the drilling can be made during daytime shifts and that the guidable drill head can be excavated and the cables fed through at a later point in time, on a single occasion when the trains are not in service, the guidable drill head can be excavated and the cables fed through. This way the train traffic, and therefore thealso passengers, experience as little inconvenience as possible. And more safety is provided to the construction people.